How did we approach this project?
Setting up the structure for a flying start
In the initial phase of the project, I worked in a small core team in which I set up and helped shape the project’s processes and structures in an integrated way. By setting up a clear and coherent information management process at the front end, I created a clear and accessible information landscape. This enabled the growing project team to get off to a good start from day one and work together effectively straight away. In the process, the planning was further shaped from a tender planning to a real project planning.
Streamlining information and integrating processes
After setting up the basics, I focused on streamlining information management. Using Primavera and Relatics, I ensured an integrated approach where time data, object data, quality information, risks, and financial data connected seamlessly. This not only provided a solid basis for project management, but also gave the team the tools to make the right decisions at any time.
4D modelling for insight and guidance
To make construction progress visual, I integrated the time model with the 3D design in Synchro 4D. This approach provided a powerful overview of day-to-day progress and enabled early identification and adjustment of critical construction phases. This not only improved communication with stakeholders, but gave the team the clarity and focus to perform within time and budget.