How did we approach this project?
Detailing the schedule
One of the most important action points was to become acquainted with and gain insight into the process of laying cables. In addition, it was important to get a handle on all the activities within a phase (CD/BD/DD)
This made it clear what everyone was responsible for, when these activities were expected to take place, and what the dependencies were. With all this information, I fleshed out the schedule so that everyone had a clear idea of what activities needed to be carried out in which phase.Detailed schedule and problem solving
During the creation of the detailed schedule, the first problems with the ongoing projects quickly became apparent. These projects were starting to fall behind schedule, in part due to the process of obtaining permission from landowners proving more complicated than anticipated. Together with the omgevingsmanagers (site managers), we decided to further break down the work. This resulted in better cooperation, more benchmarks during the phases, and a smoother, accelerated procedure for obtaining permission from landowners.
Guidance based on the schedule
Now it is important that everyone gets used to steering the projects according to the schedule and to keep them up to date. This is where I/we take the lead in getting the stakeholders on board.