How did we proceed?
Creating the general schedule
The first step in this project was to create a general schedule. Hollandia is coordinating the project and providing all the necessary documentation. Van Halteren Technologies is working on the hydraulic installations, while De Vries Piping and DuoTec are responsible for replacing the piping.
In consultation with all parties involved, I have set up an general schedule using a top-down approach that takes all interests within the project into account and ensures that all activities necessary to complete the project have been mapped out.
Coordination and communication between the parties involved
As project coordinator at Hollandia, I ensure coordination between all parties based on the general schedule. By iteratively updating the schedule with progress information and new insights, the schedule remains up to date and aligned with developments within the project.
Detailed schedule for the renovation of the piping work
To get a better grip on the implementation phase, I have drawn up a detailed schedule linked to the general schedule. By monitoring progress at a detailed level, we can closely follow the general project progress and proactively respond to any bottlenecks.